Phase V: Review by Stakeholders

Date Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Phase I II III IV V VI VII VIII

Phase V: September 2012 - October 2012

Summary

UPS Steering Group to distribute draft of UPS to all institutions' stakeholders.

September 13th - October 19th: Proposed Implementation Decisions reviewed by governance groups and other stakeholder groups.

September - October: Proposed Implementation Decisions presented to and discussed with Legislative Leaders.

After October 19, 2012, UPS Project Team to consider all suggestions and revisions to proposed implementation decision documents

Finalize the necessary technical statutory changes needed to implement the intent of s. 36.115 Wis. Stats.